Although Saturday is a day off, the works on the district roads were in full swing. Currently, employees of the PE "Stik" are laying asphalt on the main Narodna street in the village of Kryve, the press service of Tyachiv District State Administration reports.
This is one of the most complex sites with extremely neglected roads, some stretches are all potholes. Therefore, road builders cover these whole areas with asphalt, and where the course has been preserved in good condition, they do patch repairs.
The total length of the road is 4 km 840 m, more than half of which has already been repaired. The project cost is about 3 million hryvnia, it is co-funded by the district and the village budget. In some places, depending on the extent of the course damage, road builders lay 5 cm layer of asphalt. So far, there have been no disruptions with its supply. So, they plan to complete the work in Kryve according to the schedule.
Thus, people have normal roads from Ternovo to Teresva where repairs have already been completed.. Then, road builders will move to next settlements – the town of Dubove, Hanychi and towards Ust-Chorna.
Overall, this year, it is planned to repair all public roads of local importance in Tyachiv district. Press service of Tyachiv district