Deputies planning to make changes to the program of improvement of Uzhgorod, expanding the list of roads to be repaired at the expense of the city budget.
Thus, it is planned to overhaul city roads: Halan Str. – 400,000 UAH,Tlekhas Str. – 300,000 UAH, Chornovil Str. – 400,000 UAH, Pryiutsky Lane – 200,000 UAH, Starodomanynska Str. – 100,000 UAH, Stantsiyna Str. – 100,000 UAH, Tomchaniy Str. – 100,000 UAH, 8 Bereznya Str. (Mynaiska – Hrushevsky) 1,000,000 UAH, Pogorelov Str. (from Zankovetska Str. to Bohomolets Str.) – 1,317,000 UAH, Koshitska Str. – 595,000 UAH, Chelyuskinti Str. – 560,000 UAH.
Also the funds are provided for overhaul of block areas: 8 Bereznya Str., 17-21 – 723,000 UAH, Hrushevsky Str., 43,45,47,49 – 221,000 UAH, Peremoha Str., 165,167,169,171 – 350.000 UAH, 8 Bereznya Str., 3,5,7 – 350,000 UAH